Saturday, November 5, 2011

House Update

Clear Trees on the lot
Foundation
Framing 
Shingle the roof 
Pre-electrical
pre-plumbing
pre-HVAC
pre-wire for sound system 
install sofets and facia
install windows and outside doors
Put on siding
Install drywall
Lay hardwood floors, tile and carpet
Paint (almost complete)
Install cabinets and countertops (almost complete)
Trim work (in progress)
Instal light fixtures
Finish Electrical
Finish Plumbing
Finish HVAC
Landscaping 
Lay cement for driveway and garage  
Finish floors
Touch up paint and drywall nicks
Install gutters
 
 
There is light at the end of the tunnel and it feels so good!  Our closing is scheduled right now for November 14th
but it already appears that we might get moved to the 18th.   We're just so thankful to be at this point and to 
nearing the end of this 16 month adventure!
 
 
Also stay tuned to for an Audio Visual post by my husband.  He'll tell you all about the equipment we're getting 
and tell you about the audio visual company we're using and how amazing they are and their contact 
information.  
 
 
 

0 comments: